Project Status: On Going

Client: ROO

Project Name & Number: CDK CN103092

 

Mile Stones:

  1. Highest Concrete on site Casted Columns on Rumaila Oil Field with total of 6m Height each
  2. Implemented Hollow Core engineering solution to optimize time and cost first time in Rumaila Oil Field
  3. More than 1600 M3 of concrete used till now
  4. More than 65000 M3 earth works completed till now
  5. More than 5500 M3 of scaffold used till now
  6. More than 150 daily workforce activities and more than 216,000 working hours and ZERO recordable incidents till now
  7. Highest HSE & QA/QC standards are implemented  
  8. Client Satisfaction 100% till now