Inspection and cabling works for generators at BGC BNGL OPF1 & OPF2

May 24 2025 civi land

1. Installation and wiring termination of the electrical and fuel system (30KVA) for the g... [...]

BGC MCS Markazia Compressing Station project in South Rumaila

May 24 2025 civi land

1 / Inspection (ITRA)works for the power cables and earthing system .<br /> <br /> 2 / P... [...]

Transportation of the NORM by our team working on ( RWC ) project

May 22 2025 civi land

1. The company is responsible for collecting scrap pipes contaminated with Naturally Occur... [...]

Reject pump issue (FWKO)

May 22 2025 civi land

Clean and fixed strainer filters for the PWD Reject Pumps (JANU-424-P002A and JANU-424-P00... [...]

CDK Project

May 22 2025 civi land

Curtains walls insulation in CDK project (19th,20Th, May,2025) [...]

.Expansion in Chemical Services

May 14 2025 civi land

Civi Land, honored to receive Mr. Marshall Zheng (Sino Oil King Shine Chemicals Co, Ltd.-... [...]

CIVILAND CO. MANAGING DIIRECTOR SITE VISIT-CDK PROJECT(ROO-BECL) , SOUTH RUMAILA

Jan 10 2025 civi land

CIVILAND CO. Managing Director Mr. Mahdi Badda Site Visit With the CIVILAND ,CDK PROJECT T... [...]

EXPANSION OF ZUBAIR-MISHIRIF DEGASSING STATION

Dec 16 2024 civi land

CIVILAND .CO MANAGING DIRECTOR Mr Mahdi BaddaSITE VISIT WITH THE TEAM ON12/15/2024 INZUBAI... [...]

PWRI1,PWT North Rumaila

Nov 16 2024 civi land

PWRI1,PWT North Rumaila: Civi Land Team completed the Closed Drain Vessel Return pump (PW0... [...]

2024 Global Energy Forum & New Product Launch

Oct 26 2024 civi land

Maintenance Department Manager Mr. Hussein Al-Ameri participates in 2024 Global Energy For... [...]

Commissioning s Services: Mishrif Qurainat activities,

Oct 07 2024 civi land

Our mecahnical team executed pre-Commissioning activites for Corrosion Inhibitor Transfer... [...]

DS03 shutdown 18.9.2024/ Mechanical activities with CPECC

Sep 28 2024 civi land

DS03 shutdown 18.9.2024/ Mechanical activities with CPECC:<br /> <br /> 1-Attending and... [...]